Hi group,
We create a lot of resources, have a schedule in finite mode and we begin to pas the resource in finite mode. Before we do that, we want to know the capacity utilization. So, we try the report utilization inquiry. This is support cool because we know every day the load hours vs capacity. BUT we have a big problem. For weekday (Monday to Friday), the capacity is correct as per the resource calendar. But for Saturday and Monday, Visual is not using the resource calendar. Looks like it assumes we’ll work 24h Saturday, but in the resource calendar, we put 3 hours only.
Anybody have the same problem?
Thanks in advance
Nancy