Hello folks,
We have an issue with either Requisitions or the Activity- when a service Requisition is submitted using one Activity (only seeing it on this one Activity, the Requisition will still commit the funding even when the PO is released. Basically, the system code on the AC298 is RQ- but the RQ status is closed. Its the oddest thing but is also causing the Activity to be overspent. Thoughts on what could cause this? The system code on the report tells us that its the RQ causing it (other than PO). FYI- the PO hasn't been received, so it hasn't even made it to AP. Help!