Can anyone help?
We are running our machine shop using backward scheduling but it is not working well for us. We have orders due in October which are ten days late but the schedulie has allowed a 10 day gap to open at the beginning of September (presumably because the orders wanted at the end of September are on time). Why doesn't the schedule move everything backwards until the October orders are on time? There are no other operations affecting this.
Is there anything I can do to put this right or am I going to have to buy some 3rd party scheduling software?
Thanks
Elaine Slater
Hydraulic Projects Ltd