Has anyone successfully used add-ins to mass close vendor agreements on PO25? Trying to close out old agreements before they get loaded into FSM.
Thanks,
Dan
Hi, Dan.
You will not be able to close the agreement at the header level. The only actions you can do with Add-ins are Add, Change, and Delete (not Close). With that said, at the line level, you can enter 'H' (Hold) to put the lines on hold because you can do the Change action to accept the hold option.
Dave