When Infor Managed Services performs updates for us, I just get a 'range of time' 10p-6am.
I have approximately 20 IPA's on schedule nightly.
So some of the IPA's complete normally but some fail as they reboot or something in the middle of them running.
I am considering just putting them all on hold and come in early to run them manually.
But I can't seem to see how I can just put them on hold/cancel for Sunday night and Monday night...
I see them in My Actions and can just see 'next run'... I looked at some manuals but I can't see how to just 'hold' or cancel from one day in a schedule.
Any insight or recommendations would be helpful.