Our organization is in the process of restructuring the way we utilize our MRP with lean manufacturing in mind. Our date collected is over 10 years old and over time, we've lost touch of standardizing and managing the data that is going in (forgetting to clock in/out of WO's, not logging correct quantity, setting up parts with incorrect PPH/setup). Because of this, we have bad data to manage off of.
Efficiency, utilization is completely off, which means we cannot use the Concurrent scheduler the way it's intended to be used for. We have random resource ID's that are duplicate with no efficient way of grouping..
First step is to cleanup the resources and update the PPH using what "good" data we have from labor tickets. Ideally we can get these close enough to implement a standard process for our building managers to then mange to (adding the responsibility of ensuring it continues to be updated).
I'm reaching out for ANYONE that has experienced this transition and can provide some insight. Any and all feedback is appreciated!
-Caleb