Hi,
In material planning windows, we have two columns the release and the suggested release date. The Sug release date it’s the due date minus the planning Leadtime in calendar week. The release date it’s the due date minus the planning Leadtime for manufacturing week (Monday to Friday, exception not include). We are working 24h/7d, so we want to align the Release date and Sug Release date. We try to uncheck in site maintenance “Use Global Calendar and exception” and we obtained the same result: they are still not aligned.
Thanks for all help you can give me
Nancy