Hi,
On a phantom item, the materials are "exploded" or "blown-through" to the top level Production BOM when the Job is released/Copy Routing BOM is performed. However any Operations on the phantom item are not appearing on the Production BOM.
Has anyone found or knows a way to also explode the Operations into the Production BOM?