Is anyone using allocations for actuals in M3 and also using the same configuration for budgeting?
I can’t get the budget allocations to work when trying to run 2 allocations that overlap. I've been informed by our consultant that we can have overlapping allocations - if we assign the templates correctly. I tried setting the allocation level (didn’t work) and tried changing the Calc fr level (didn’t work). Can you please help me understand what I did wrong? Here’s my research:
I'm using a single account (50030) and cost center(610950) for the Cash Discounts, no Brand assigned in the Budget upload
When loaded to M3, we see the negative amount correctly
And when copied into EPM, we see that amount for the year correctly with no Brand assigned
I created this test allocation template with only 2 rows where cash discounts are assigned to be allocated.
When those allocations are run together, the allocation is duplicated (or ran twice using the original data), resulting in a positive value in the N.A. Brand rather than zero.
Our consultant suggested I change the 2nd step Cal fr level to attempt to calculate from the previous step
But that doesn’t work either. It gives me different, but still incorrect, results. The N.A. Brand value should be zero. Any idea as to what I am doing wrong?