We use Planned Purchase Orders (PPS170) to generate sub-contract Purchase Orders (MRP items) and Raw Material/Packaging Firm PO's. We run full Regen MRP every night. We recently changed the credit terms for a few suppliers. This creates an issue when releasing multiple Planned Purchase Orders (pPO's). The pPO's generated prior to the Supplier Master update have the original Credit Terms. New pPO's have the updated Credit Terms. Since the Credit Terms are different, we can not combine multiple pPO's into one (1) Firm PO.
Has anyone found a process to do a mass update to the pPO's in PPS170 to accommodate an update to the Supplier Master and Addresses?
Thank you in advance