Hi,
On the left side of the screenshot you see the material plan for an item on the warehouse of a production unit. It has a planning time fence of 25 days. The production unit is closed for two weeks and based on the system calendar it sets the date to 2024-01-25.
The right side of the screenshot is the material plan for the same item in the warehouse of a distribution center. The item is distributed from the production unit mentioned above. In this warehouse the planning time fence is set to 27 days, but because the system calendar in this division does not have two weeks of closure the date for the planning time fence is 2025-01-14. I.e. it's earlier than for the PU even though the planning time fence is longer.
Is there any way to take the system calendar for the supplying warehouse into consideration when the planning time fence is calculated in MMS080? Otherwise we might release distribution orders with incorrect planned dates. From my investigation I have not seen that distribution calendars sorts this out.
Thanks!

Best Regards,
Dan