Production Leveling
I am trying to find a way to use Production Leveling with MRP. I would appreciate any help or insight to make this happen.
An example: We have many products that have their peak season in November and December. The forecast shows that January through September, we will sell 10,000 products every month. October we will sell 20,000, November we will sell 100,000, and December we will sell 350,000. Based on the leadtime of 60 days and a 3 month average safety stock, MRP tells us that we need to start ordering the bulk of our products on September 1st.
The problem with this is that the production facility does not have the capacity for this, even after extending their hours and hiring temps.
We don't want to manipulate the forecast- it's a real forecast and it is what it is. Within Visual, is there a way to create a level production plan throughout the year without manipulating real data?