Hi there,
This year has 53 calendar weeks, which is why we want to maintain 53 calendar weeks in our system calendar on CRS910 as well (which doesn't work how we want it to). We have already created Infor incidents, but they were unable to help us further. Here is what we have done so far:
- Switched to division BLANK
- Deleted the entries on division 100 and BLANK in table CSYPER using the BE Data Management
- Set the number of calendar weeks to 53 in MNS100/F, period type 2 (field NPT2)
- Then opened the 2026 period type 2 entry in CRS910 using “edit”
While calendar week 53 now appears, the calendar days are incorrect.
Does anyone know the correct procedure for adjusting the system calendar?
We want to have 7 Caldys, 5 Wrkdys and 5 Bnkdys for each calender week in period type 2 for year 2026.
At the moment it looks like this:
//Dominique