I am not sure why MRP plans work orders for a longer period of time than what my lead time is. besides firming up all planned orders, is there any way to adjust these dates (release and due) to mirror my lead times? or is there something I am over looking to have the system do the work for me? I don't want to do the route of firming up all planned because it will be too much to continue to massage and maintain because a lot of my customer orders are on LTA's going out 1-4 years. this stretching of the suggested release dates on the planned orders is giving my false material requirements for sub assemblies and raw materials. I am running 7.1.2.